What Is Retention?
Retention is a percentage of each progress payment that the client (or head contractor) withholds during construction as security that the contractor will finish the works and rectify any defects that appear afterwards. It builds up as the job progresses, is capped at an agreed percentage of the contract sum, and is released in stages — commonly part at practical completion and the balance at the end of the defects liability period.
Key takeaways
- Retention is a percentage — commonly around 5% — withheld from each progress payment as security for completion and defects, not an extra cost on top of the contract price.
- Retention accrues progressively and is usually capped at a total percentage of the contract sum, after which no further retention is deducted from later claims.
- It is typically released in two instalments: part at practical completion, and the remainder after the defects liability period once any defects are made good.
- Some contracts allow a retention bond or bank guarantee instead of cash retention, freeing up the contractor’s cash flow during the job.
- My Trade Hub’s progress claim tools track retention automatically against each claim, so the amount held, released and still outstanding is always visible.
What is retention?
Retention is a mechanism written into most construction contracts that lets the party paying for the works hold back a slice of each progress payment, rather than paying the full claimed amount every time. The withheld amount is not lost to the contractor — it is money the contractor has earned but has not yet been paid, held as security until the job is properly finished.
The purpose is to give the client leverage to ensure the contractor returns to complete outstanding items and fix defects, without the client having to chase a contractor who has already been paid in full and moved on to the next job. It is one of several forms of security used in construction contracts, alongside performance bonds and bank guarantees, and is common on residential and commercial work of every size.
In plain terms
Retention is the client keeping back a small slice of every payment — like a deposit in reverse — released once the job is finished and any defects are fixed.
How retention is calculated
Retention is usually expressed as a percentage of each progress claim, deducted before payment is made, and it keeps accruing claim by claim until it reaches an agreed cap. A typical structure:
- Percentage per claim — commonly around 5% of the value of each progress payment, though the figure is set by the contract and varies by project type and risk.
- Overall cap — retention usually stops accruing once it reaches a set percentage of the total contract sum, often also around 5%.
- Retention trust accounts — in some Australian states, retention above a threshold on eligible projects must be held in a separate trust account for the contractor’s protection.
- Retention bonds or bank guarantees — many contracts allow the contractor to substitute a bond or guarantee for cash retention, improving cash flow during the build.
| Claim | Claim value | Retention withheld | Cumulative retention | Amount paid |
|---|---|---|---|---|
| 1 | $120,000 | $6,000 | $6,000 | $114,000 |
| 2 | $150,000 | $7,500 | $13,500 | $142,500 |
| 3 | $90,000 | $4,500 | $18,000 | $85,500 |
When retention is released
Retention is released in stages tied to contractual milestones, not all at once at the very end of the job. The most common structure splits it in two: half (or another agreed proportion) is released at practical completion, when the works are fit for use apart from minor outstanding items, and the balance is released at the end of the defects liability period, once any defects identified during that period have been rectified.
The defects liability period itself is commonly around 12 months from practical completion, though it varies by contract and project type. Some contracts release retention in more than two tranches, or tie partial release to specific milestones such as the completion of particular trades or sections of the works — the release schedule is always set out in the contract, so it is worth checking rather than assuming a standard split applies.
Retention vs other forms of security
Retention is one of several tools a client can use to secure a contractor’s performance, and contracts sometimes combine more than one. A performance bond or bank guarantee provides similar security without touching the contractor’s cash flow during the job, since it is arranged with a bank or surety rather than deducted from payments.
Because retention directly reduces cash in hand during construction — often at the point in a job when cash flow is already tightest — many contractors prefer to negotiate a bond or guarantee instead, where the contract and the client’s risk appetite allow it. Larger, well-capitalised contractors more commonly secure this substitution than smaller subcontractors, who are more often the ones retention is withheld from.
- Cash retention — withheld from progress payments, released at agreed milestones.
- Retention bond or bank guarantee — a third party stands behind the contractor’s performance instead of cash being withheld.
- Performance bond — broader security, often used on larger projects, covering performance generally rather than just defects.
Retention and cash flow
Because retention is deducted from money already earned, it has an outsized effect on a contractor’s cash flow — every claim pays out slightly less than the work is worth, and the shortfall is only recovered much later, at practical completion and again after the defects liability period. For subcontractors carrying retention across several head contracts at once, this can tie up a meaningful slice of working capital for the better part of a year or more.
Good practice is to track retention on every job explicitly — how much has been withheld, when each release is due, and what conditions (such as a defects list being closed out) must be met first — rather than treating it as an afterthought once the final account is settled. Chasing a retention release six months after it was due is far harder than tracking it against the contract from day one.
Who is entitled to retention, and who holds it
Retention typically flows down the contract chain: a client withholds retention from the head contractor, and the head contractor in turn commonly withholds retention from subcontractors on the same basis. Each party in the chain is entitled to have retention held fairly and released on time under their own contract, regardless of what is happening further up the chain.
In several Australian states, security of payment and retention trust account legislation now requires retention above a threshold on eligible projects to be held in a separate trust account, specifically to protect subcontractors if a head contractor becomes insolvent before releasing retention that is properly due. The detail differs by state, so it is worth checking the current rules where the project is located.
Retention vs liquidated damages and defects
Retention is often mentioned in the same breath as other end-of-job contract mechanisms, but each serves a different purpose:
- Retention vs liquidated damages — retention secures completion and defect rectification; liquidated damages are a pre-agreed daily rate charged if the contractor finishes late, and are a separate deduction entirely.
- Retention vs the defects liability period — the defects liability period is the timeframe during which defects must be rectified; retention is the financial security held over that same period.
- Retention vs a variation — a variation changes the scope and price of the works; retention is a payment security mechanism, unaffected by whether variations have occurred.
Common mistakes with retention
Retention disputes are common, and most come back to a small set of avoidable issues:
- Not checking the contract’s retention percentage and cap before pricing the job, which can understate the cash flow impact of a large contract.
- Losing track of how much retention has been withheld across multiple progress claims, making the final reconciliation harder than it needs to be.
- Missing the practical completion or defects liability period milestones that trigger release, so money that is due sits unclaimed.
- Not knowing whether a retention trust account applies on a given project, and failing to check that retention is actually protected as required.
How My Trade Hub helps you manage retention
My Trade Hub’s progress claim tools calculate retention automatically against every claim, applying the correct percentage and cap so you always know exactly how much has been withheld, how much has been released, and what remains outstanding.
Because retention is tracked against the same platform used to prepare your original priced estimate and progress claims, nothing slips through the cracks between tender and final account — freeing up the time you would otherwise spend reconciling retention by hand, as part of an estimation and claims workflow built to run 60-75% faster than manual estimation.
Frequently asked questions
When is retention released?
Retention is usually released in two parts: a portion at practical completion, and the balance at the end of the defects liability period once defects are rectified. The contract sets the exact split and timing, so it is worth checking rather than assuming a standard schedule applies.
How much retention can a client withhold?
It varies by contract, but a common structure withholds around 5% of each progress payment, capped at a total of around 5% of the contract sum. Some contracts set different percentages or caps, so always check the specific wording.
What is the difference between retention and a bank guarantee?
Retention is cash withheld from progress payments and released later. A bank guarantee provides similar security to the client without reducing the contractor’s cash flow during the job, since a bank or surety stands behind the guarantee instead of money being deducted from claims.
Is retention held in a separate trust account?
On some larger projects and in some Australian states, retention above a threshold must be held in a separate trust account to protect subcontractors if a head contractor becomes insolvent. The rules differ by state and project size, so check what applies to your contract.
Can a subcontractor be charged retention too?
Yes. Retention commonly flows down the contract chain — a head contractor often withholds retention from subcontractors on the same basis the client withholds it from the head contractor, under each subcontract’s own terms.
What happens to retention if the builder goes insolvent?
This is precisely the risk retention trust account laws are designed to address in several Australian states — protecting retention held for subcontractors so it is not lost in an insolvency. Without that protection, unreleased retention can become an unsecured claim in the insolvency.
Ready to win more work?
Turn your plans into professional tenders 60–75% faster with My Trade Hub. Plans built around your tendering volume — no lock-in contracts.
Get started free